How long does a rewire take?

The electrical work on a three-bedroom house is 5 to 7 days. That is the number you will be quoted, and it is accurate. It is also about a third of the answer — because the rewire is not finished when the electrician leaves, and the house is realistically disrupted for three to four weeks.

The electrician's part

PropertyElectrical work
Two-bedroom flat4–6 days
Three-bedroom house5–7 days
Four-bedroom detached8–10 days
A single roomAbout a day

That splits into first fix — floors up, walls chased, cables run, back boxes in — and second fix, where accessories go on, the board is installed and everything is tested and certified. First fix is the destructive half and the noisy one. Second fix is quieter but it is when the power goes off and on repeatedly as circuits are terminated and tested.

The part nobody schedules

Here is the full timeline for a three-bed, written the way you will actually live it:

StageDurationWhat it is like
First fix3–4 days Floorboards up, walls chased to brick, dust everywhere, power off in sections
Second fix, testing, certification2–3 days Quieter; power comes and goes; you get the certificates at the end
Plastering2–4 days' work Usually a different trade, and usually not in the electrician's quote
Plaster dryingA week or more Nothing happens. You cannot decorate. This is the stage that is always forgotten
Decorating3–7 days Mist coat first, then proper coats
Floors and carpets back1–2 days The end
Total3–4 weeks
Plaster drying is the reason rewires "overrun" when nobody has overrun. The electrician finished on day seven, exactly as quoted. But fresh plaster needs to dry before it takes paint, and rushing it produces patchy, peeling decoration you will pay to redo. Thick patches, cold weather and a house with the heating off — which it partly will be — all extend it. Build a week of nothing into your plan and you will not be surprised.

Can you live in it?

Yes, and plenty of people do and wish they had not. The honest picture: floors are up, so the route between rooms changes daily. Plaster dust gets into everything, including things in closed cupboards. Power is off circuit by circuit, so the kettle, the router and the freezer are all periodically unavailable. It is manageable for an adult working elsewhere. It is genuinely hard with small children, a newborn, anyone working from home on calls, or anyone shielding.

The fix: ask for it staged

Almost every rewire can be sequenced floor by floor so that one half of the house stays habitable while the other is worked on — upstairs first, then down, or the reverse. You keep a working kitchen or a working bedroom throughout.

It costs a little more in labour, because the electrician sets up and strips out twice and cannot run cables in the most efficient order. It costs far less than renting somewhere for a month. The critical thing is to ask for it before the quote is written — staging a job that was priced as a single continuous run is a variation, and variations are where quotes go wrong.

What makes it take longer

What makes it quicker

  1. Decide the socket and light positions before day one, room by room, in writing. Walk the house with a pencil.
  2. Clear the rooms properly. Every item still in a room is an item that has to be moved twice.
  3. Lift the carpets yourself if you can — it is unskilled time you are otherwise paying for.
  4. Book the plasterer before the electrician starts, for the day after second fix. Waiting to find one afterwards adds a week of nothing.
  5. Only do a partial if a partial is what you need. Read whether you need a full rewire first — a partial is days rather than weeks.

Before you commit

Get the timeline and the making-good in writing together, because they are the same question: a quote that ends at second fix is a quote that ends with chased walls. The full cost picture, including the plastering that is usually excluded, is on the full rewire cost breakdown. And confirm whoever you hire is on the Registered Competent Person Electrical register, because a rewire is notifiable and the certificate is what you are really buying.

Get a rewire quote with a timeline in it

Tell us the property size and whether you need the work staged to stay in the house. A quote with a sequence in it is worth more than a cheaper one without.